Thursday, March 26, 2015

Update

Building A - 1st floor hallway and unit separation walls are being built. 



Building B - precast is being set. 


The footings are also being poured for the connector. 




Friday, March 13, 2015

Update

Building B - the foundation will be complete next week. 










Building A - first floor exterior walls are going up. 















Monday, March 2, 2015

Update

Pre-cast on building A is set and is being grouted today. Framers are starting on Wednesday. 

Building B foundation progress. 




Monday, February 9, 2015

Update

Pre-cast is being set on building a and building b foundation is going in. 









Wednesday, January 21, 2015

Foundation

We have one more pour to complete the walls before pre-cast. 




Saturday, January 17, 2015

Tuesday, December 16, 2014

Start

The foundation is dug and we are preparing to pour footings.