Friday, September 11, 2015

Update

Retaining walls are being finished. 


Exterior is progressing. 



We are insulating 1st floor and the connector / clubhouse building. 



Friday, August 28, 2015

Update

Building A - 3rd floor is primed. Texture today and paint on Monday. 




The siding is also starting to come along. 



Building B - 2nd floor exterior walls are going up. 







Monday, August 17, 2015

Update

3rd floor drywall is being taped. 


Parking lot is graded out and we are forming the bumper sidewalks. 



Retaining walls are being formed. 





Thursday, August 13, 2015

Update

Footings are being formed for the retaining walls by the overhead doors. 


Parking lot is in - working on final prep for curbs and sidewalk walk. 


Clubhouse - roof is almost dried in. 



Thursday, August 6, 2015

Project Update

The roof of the clubhouse is being sheathed. We will start the roof Tuesday.
 

 
The first building - nearly all wrapped up with windows and patio doors installed.


Units are starting to get insulated and drywalled.


 

 

The main entrance to the clubhouse
 




Tuesday, July 21, 2015

Update

Exterior of building A is getting wrapped up. 


The clubhouse floor is getting poured and building B 1st floor exterior walls are going up. 



Tuesday, June 23, 2015

Update

1/2 the roof is complete. 
Trades are starting to get going on 3rd floor. 



Tuesday, June 16, 2015

Update

1/2 of the roof is sheathed and the rest of the roof trusses are being set. 




Wednesday, May 13, 2015

Construction Update

3rd floor trusses are being set. The parking garage is being poured.




Monday, April 27, 2015

Update

2nd floor exterior walls are going up. Stairs are being built. The clubhouse is being back filled. 








Tuesday, April 14, 2015

Friday, April 3, 2015

Update

Building A - 2nd floor trusses are being set and underground plumbing is being installed. 







The club house footings have been poured and we are starting building B underground. 





Thursday, March 26, 2015

Update

Building A - 1st floor hallway and unit separation walls are being built. 



Building B - precast is being set. 


The footings are also being poured for the connector.